| 2001 Construction Projects | |
| Construct Recreational Lodgings at Bellows AFS | $870,348.77 |
| HECO Kewalo 138kV Substation Phase 1B | $477,642.00 |
| Salvation Army Termite Repairs at Camp Homelani | $203,105.00 |
| Salvation Army Parking Lot at Manoa | $60,527.00 |
| Coca-Cola Bottling Co. of Hawaii Miscellaneous Repairs at Pukoloa Street | $430,171.00 |
| University of Hawaii Soccer & Football Field Improvements Storage Shed | $350,675.00 |
| Lyle Asaoka House Repairs | $162,446.26 |
| Coke Fountain USA Tanker Bay | $79,744.00 |
| Al Phillips The Cleaners New Fire Meter | $28,153.00 |
| Colliers Monroe Friedlander, Inc. Mark's Garage Metal Roof Demolition | $47,358.00 |
| Daiei, Inc. Seal Coat & AC Repairs | $67,863.00 |
Construct Recreational Lodgings at Bellows AFS
![]() |
Recreational site lodgings, single story structures of wood framed construction on concrete slab-on-grade. Each lodging has a kitchen, living room, and lanai. The structures have exterior and interior finishes including appliances, cabinets, electrical lighting, communication, fire detection system, supporting utilities and all materials needed to provide a complete and usable building. Construction conformed to the latest handicap accessible guidelines. |
|
||
![]() |
![]() |
|||
|
|
|
|
|
Construct Recreational Lodgings Bellows Air Force Station |
|
Hawaiian Electric Company Kewalo 138kV Substation Phase 1B |
|
|
|
|
|
Salvation Army Termite Repairs at Camp Homelani |
Salvation Army Parking Lot Manoa Headquarters |
|
|
|
|
|
|
Coca-Cola Bottling Co. of Hawaii Miscellaneous Repairs at Pukoloa Street |
Lyle Asaoka House Repairs |
|
|
|
||
|
Walker-Moody 773T Bobcat |
||
|
|
University of Hawaii Soccer & Football Field Improvements Storage Shed
|
|
|
|
||
|
|
|
A new pre-engineered metal building with grading, utilities, excavation, foundations, drainage system, water system, sanitary sewer system, concrete, masonry, miscellaneous metals, chain link fence, sealants, overhead rolling doors, finish hardware, painting, miscellaneous specialties, plumbing, electrical, and miscellaneous related work. |
| 2002 Construction Projects | |
| Hawaiian Assets Management 444 Waiakamilo Road Fire Reconstruction | $418,283.00 |
| Citi Financial Tower Protective Netting | $30,000.00 |
| Hawaii Food Bank Building Demolition | $36,550.00 |
| Salvation Army Manoa Headquarters Parking Lot Reconstruction | $41,861.00 |
| Palolo Valley Housing Miscellaneous Site Improvements | $451,098.00 |
| Salvation Army New Office Trailer | $436,385.00 |
| Coca-Cola USA Fountain Office Renovation | $50,109.00 |
| Salvation Army Miscellaneous Site Work Manoa | $47,224.00 |
| Tesoro Exc Pipeline at Aole Street | $32,048.32 |
| Bank of Hawaii Waialae Kahala Branch Addition & Office Alterations | $1,366,694.00 |
| Tesoro Komohana Street Pipe Repairs | $95,243.75 |
| Sony Hawaii Mezzanine Second Stairs | $47,034.00 |
| Tesoro CGU Bullet Containment | $80,000.00 |
Bank of Hawaii Waialae Kahala Branch Addition & Office Alterations
![]() |
![]() |
![]() |
||
|
Approximately 6,000 s.f. of interior renovation and 1,600 s.f. of office addition. The bank was operational while the work was being performed. Site work included exterior lighting, landscaping & irrigation, AC paving, interior & exterior demolition, concrete, structural steel, metal decking, cold form framing, stainless steel handrails, finish carpentry, building insulation, direct applied exterior finish system, built-up bituminous roofing, flashing & sheet metal, wood doors, all glass entrances & storefronts, aluminum windows, finish hardware, glazing, cement plasters, gypsum board, ceramic tile, acoustic ceiling, wood flooring, resilient base, carpeting, painting, plumbing, A/C, and electrical. |
![]() |
|||
The Salvation Army New Office Trailer
|
|
|
|
||
|
|
|
|
||
|
|
Project consisted of removal and replacement of a modular office trailer approximately 24' x 42', utilities excavation, offsite and onsite waterline main line for fire hydrant and new sprinkler system to trailer, clsm fill under roadway, cold plane asphalt, asphalt paving, roadway striping and pavement marking, concrete sidewalks, metal handrails, concrete, carpentry, painting, firesprinkler, plumbing, electrical work. |
|||
| 2002 Seal Coating Projects | |
| 91-110 Hanua Street Seal Coating | $16,207 |
| Daiei Waipahu Seal Coating & AC Repairs | $200,478 |
| Chaney Brooks Hamakua Seal Coating & AC | $22,353 |
| HRI Laie Shopping Center Seal Coat | $51,931 |
| Space Place Seal Coating & AC | $25,346 |
| Yacht Club Seal Coating & AC Terrace | $36,788 |
| Ching William Henry Road Seal Coating | $22,140 |
Hawaiian Assets Management 444 Waiakamilo Road Fire Reconstruction
|
|
|
|
||
![]() |
Hawaiian Assets Management 444 Waiakamilo Road Fire Reconstruction
Work consisted of demolition of existing building, which was severely damage by fire. Replaced with a new metal building to match the existing building and interior offices. |
|||
|
|
||
|
Citi Financial Tower Protective Netting
|
||
|
|
|
|
|
Salvation Army Installing Water Line |
91-110 Hanua Street |
|
|
|
|
|
|
Salvation Army Manoa Headquarters Parking Lot Reconstruction |
Salvation Army Manoa Headquarters Parking Lot Reconstruction |
|
|
|
|
|
|
Hawaii Food Bank Building Demolition |
Palolo Valley Housing Miscellaneous Site Improvements |
|
|
|
|
|
|
Tesoro Underground Pipe Repair Campbell Industrial Park |
Office Staff At The Canoe Club For Secretary's Day | |
Tesoro CGU Bullet Containment
|
|
|
|
||
|
|
Work at the Tesoro Refinery consisted of pouring a concrete slab under gas vessels and constructing a containment berm with a gunite finish. |
|||
|
Checking out the SealMaster headquarters in Ohio. Lyle Moody and Chris Laird |
||||
|
|
|
|
||
2003
The Start of A New Company
After seeing the need for a full service asphalt products manufacture store in Hawaii and the success that Walker-Moody Construction Co. Ltd. has had in seal coating, Walker-Moody Pavement Maintenance Products and Equipment, dba SealMaster Hawaii, has opened for business.
![]() |
||
![]() |
![]() |
|
| 2003 Construction Projects | |
| Salvation Army Camp Homelani Termite Repairs | $197,500.00 |
| U.S. Department of the Interior Construct Storage Building at The James Campbell National Wildlife Refuge | $363,897.00 |
| Hawaii Food Bank Building A Demolition | $69,000.00 |
| Bank of Hawaii Investments Group Opelo Plaza Repairs | $40,595.48 |
| Bank of Hawaii Investments Group Pines Plaza Kona | $197,275.00 |
| Daiei Waipahu Freezer Slab | $33,505.00 |
| Tesoro Pump Pad & Pipe Support | $33,378.13 |
| Daiei Renovate Waipahu Annex | $126,250.00 |
| Daiei Kaheka Central Pacific Bank Renovation | $33,152.00 |
| The Estate of Samuel Damon Reroof Plywood Hawaii | $86,000.00 |
| Bank of Hawaii Investments Group Pines Plaza Shear Walls | $39,510.00 |
| AGS Engineering Sunset Beach | $22,534.00 |
| Bank of Hawaii Investments Group 318 Kinoole Street Renovation & Demolition of Existing Building | $307,251.00 |
Department of The Interior Construct Storage Building at
The James Campbell National Wildlife Refuge
![]() |
|
|
||
|
|
![]() |
|
||
|
|
A new
80' x 40' pre-engineered metal storage building, |
|||
The Salvation Army Camp Homelani Termite Repairs
|
|
|
|
||
|
|
|
|
||
|
Termite
repairs and upgrading of existing guest facility. Work included selective demolition, concrete, rough and finish carpentry, asphalt shingle roofing, wood doors, hardware, vinyl windows, gypsum board, ceramic tile, resilient flooring, painting, plumbing, and electrical. |
|
|||
|
|
|
|
|
Hawaii Foodbank Building II Demolition |
|
Hawaii Foodbank New Concrete Slab |
|
|
|
|
|
Marc Moody Industrial Complex Walker-Moody Investment |
Lyle Moody and Daughter Meagan Fishing In Alaska |
|
|
|
|
|
|
Daiei Kaheka Central Pacific Bank Renovation |
|
Daiei Waipahu Freezer Slab |
|
|
|
|
|
Daiei Renovate Waipahu Annex |
Bank of Hawaii Investments Group Pines Plaza Kona |
|
|
|
![]() |
|
|
Bank of Hawaii Investments Group 318 Kinoole Street Renovation & Demolition of Existing Building |
The Estate of Samuel Damon Reroof Plywood Hawaii |
|
|
|
||
|
Lyle & Ross Moody at The World of Concrete Convention Checking Out New Equipment |
||
| 2003 Seal Coating Projects | |
| Church of Jesus Christ Latter Day Saints Seal Coat Waimanalo | $18,597.00 |
| The Salvation Army Seal Coat Manoa Campus | $16,364.00 |
| Daiei Kailua Seal Coat & AC | $58,279.00 |
| The Yacht Club Seal Coat & AC | $18,126.00 |
|
|
|
|
|
Church of Jesus Christ Latter Day Saints Seal Coat Waimanalo |
|
The Yacht Club Seal Coat & AC |
|
|
|
Walker-Moody Construction 2003 Christmas Party |
![]() Maile Moody is the oldest daughter of Lyle Moody, and the fourth generation of the Moody family to work at Walker-Moody Construction. She graduated from Brigham Young University in Provo, Utah, with a bachelors degree in Science in Construction Management. Maile joined Walker-Moody Construction Co, Ltd. in January 2004. She holds a CQC certification issued by the Corps of Engineers and has an OSHA safety card for a 30-hour Occupational Health & Safety Training Course. As Maile puts it, she will be the first female president of the company, and she is well on her way to this goal. Maile and her father often spend time out on projects together. She excels in project management and estimating, and really takes pleasure in the work. Maile was accepted into the Master's Degree program in Construction Management at BYU Provo, and will leave Hawaii in January 2005 to pursue this next level in her education. She is on track to graduate from the program in 2006. |
| 2004 Construction Projects | |
| Walker-Moody/Marc Moody Industrial Complex |
Investment Property |
| Hawaii Foodbank Phase II | $1,993,827.97 |
| Operating Engineer Local Union No. 3 Joint Apprenticeship Committee for Hawaii Kahuku Training Center Maintenance Building | $1,139,239.45 |
|
Operating Engineers Local Union No. 3 Joint Apprenticeship Committee of Hawaii Kahuku Training Center Water Tank & Appurtenances |
$233,105.00 |
| Thompson New Driveway & Miscellaneous Site Work | $184,710.42 |
| Bacon Universal Remove & Replace Roof | $114,164.00 |
| Tesoro Flare Gas FDN & Paving | $262,750.90 |
| Haig Site Work | $274,239.00 |
| Coke Reroof Production Area | $27,400.00 |
| Daiei Kaheka Roof Repairs | $96,661.00 |
| Department of Transportation Dillingham Airfield Septic Tanks | $53,986.00 |
| Daiei Pearl City Meat Kitchen | $40,912.00 |
Marc Moody Industrial Complex
|
|
|
|
||
|
|
![]() |
|
||
|
Marc Moody Industrial Complex owned by Walker-Moody Construction Co., Ltd. and is a design build project including a two acre lot with all site work. A one-half (50'-0" x 242'-0") one user section with open and inset front two bay, two-story office entry and open and enclosed warehouse sections. The other half (50'-0" x 242'-0") with eleven each rental spaces including individual 14'-5" H x 14'-0" W roll-up doors and a community men's and women's restroom facilities. All exterior and interior walls are constructed with pre-engineered materials. The building also utilizes a continuous fascia and overhang to naturally ventilate all the storage spaces and provides a pleasing architectural "hat". |
|
|||
Hawaii Foodbank, Phase II
|
|
|
|
||
|
|
|
|
||
|
A design/build project with a new warehouse, distribution and office. This project's design, permits and construction were required to be completed in two phases, starting with Phase I in 1993 and Phase II on June 1, 2004. The work performed provided approximately 31,200 square feet under one roof including, demolition, earthwork, utilities, sewer system, cast-in-place concrete, reinforced masonry, structural steel, steel joists, steel floor decks, cold-formed metal framing, metal fabrication, carpentry, membrane waterproofing, roofing, rolling service doors, recessed loading dock, pre-engineered metal buildings, hydraulic passenger elevator, fire extinguishing sprinkler systems, plumbing, refrigeration and freezer, air conditioning, and fire alarm system. |
|
|||
Operating Engineers Local Union No. 3 Joint Apprenticeship Committee of Hawaii
Kahuku Training Center Water Tank & Appurtenance
![]() |
![]() |
![]() |
||
![]() |
The project consisted of sitework and concrete foundations for the installation of a 67,000-gallon metal water tank. Specific work included site clearing and grubbing, grading, excavation and backfilling for utilities and foundation, rip rap drainage outlet, chain link fencing and gates, aggregate roadway, reinforced concrete jacketing, reinforced concrete foundation and slab, installation of owner furnished metal water tank, miscellaneous painting, owner installed electrical work, water level sensor and signaling devices. |
|||
Tesoro Flare Gas FDN & Paving
|
|
|
|
||
|
|
|
|
||
|
This Tesoro project consisted of civil sitework and concrete foundations for the installation of above ground refinery equipment and vessels. Specific work included site clearing and grubbing, grading, probe and grouting for underground cavities, foundation drilling, excavation and backfilling, underground electrical grounding and conduit work, concrete electrical ductline jacketing, reinforced concrete foundation, slabs, and pedestals, concrete paving. |
||||
Operating Engineers Local Union No. 3 Joint Apprenticeship Committee of Hawaii
Kahuku Training Facility Maintenance Building
![]() |
![]() |
![]() |
||
![]() |
This project consisted of sitework utilities for water, fire sprinkler, sewer, and electrical. Installation of a precast concrete septic tank and leach field system. Excavation and engineered fill for the building structure. Construction of a 6,986 sf pre-engineered metal building with office and mezzanine storage. Specific components included: 10” reinforced concrete slab, embedded steel track, 4’ high reinforced concrete abuse wall, masonry at spaces under Mezzanine and around Oil Storage room, miscellaneous metals including curved under hung hoist rail, cabinetry, metal doors and windows, cold form metal framing for Oil Storage room, acoustical ceilings, resilient flooring, epoxy painting, visual display boards, wall louvers, toilet and bath accessories, hoist, cable and hose reels, pre-engineered metals building with 22 gage metal roof, wall, liner material, mechanical plumbing, compressed air piping, fire sprinkler, AC and ventilation, electrical. |
|||
|
|
|
|
|
Thompson Residence New Driveway & Miscellaneous Site Work |
|
Bacon Universal Remove & Replace Roof |
|
|
|
|
|
2,000 Gallon Water Truck |
|
Ross and Grandson John Checking Out Walker-Moody Property in Waipo Valley on the Big Island |
|
|
||
|
Haig Site Work |
||
|
|
|
Operating Engineer Local Union No. 3 Joint Apprenticeship Committee for Hawaii Kahuku Training Center Maintenance Building |
|
|
| 2004 Seal Coating Projects | |
| Salvation Army Manoa AC Repairs & Sealcoat | $88,713.00 |
| Hawaiiana Management Makiki Palms Sealcoat | $16.924.00 |
| First Church Sealcoat & AC | $25,755.00 |
| Daiei Kaheka Sealcoat First Floor | $56,342.88 |
| Pacific Eye Sealcoat & AC | $14,655.00 |
| Bradley Sealcoat | $4,980.00 |
| Church of Jesus Christ Latter Day Saints Seal Coat Mililani Stake Center | $18,550.00 |
| Salvation Army Sealcoat & AC Sumner Street | $34,721.00 |
| Church of Jesus Christ Latter Day Saints 622 Judd Street AC Overlay & Berm | $24,879.00 |
| Alamo Car Rental Sealcoat & AC | $14,997.00 |
| Marukai Sealcoat & AC | $61,170.00 |
|
|
|
|
|
Salvation Army Manoa AC Repairs & Sealcoat |
Hawaiiana Management Makiki Palms Sealcoat |
|
|
|
|
|
|
First Church Sealcoat & AC |
Daiei Kaheka Sealcoat First Floor | |
|
|
||
|
Bradley Sealcoat |
||
|
Walker-Moody Construction Co., Ltd. celebrates 110 years of service to the Hawaiian Islands with a company party aboard the USS Missouri. Ross Moody talked about Walker-Moody Construction Co., Ltd.'s deep roots with the military over the years and projects that surrounded Pearl Harbor. |
![]() |
|
|
|
|
|
|
|
|
|
Dale & Sarah Rowley |
|
Lyle & Dawna Moody |
|
|
|
|
|
|
|
Carl Higa |
|
Chris Laird & Daughter |
|
|
|
|
|
|
|
|
|
|
|
Mike & Mitzi Arakaki |
|
Lyle & Jane Asaoka |
|
|
|
|
|
|
|
Keenan & Terry Wilson |
|
Buster, Chevy & Kaena Place |
|
Abel Medeiros & Daughter |
|
|
|
|
|
|
|
Lani & Leticia Agustin |
|
Junior Prieto & Family |
|
Ron & Karen Incillo |
|
|
|
|
|
|
| 2005 Construction Projects | |
| Hawaiian Electric Company - New Kuahua Substation (Phase 1) | $2,106,744 |
| Haig - Concrete Parking Deck | $302,769 |
| Coca-Cola Kauai - Facility Renovation | $93,000 |
| Hawaii Stage & Lighting - Re-roofing | $57,183 |
| Salvation Army Manoa - Main Building Alterations | $199,412 |
| Coca-Cola Production Plant - Re-roofing | $34,449 |
| Tesoro - Control Building Wastewater System | $37,700 |
| Advanced Manufacturing Technologies (Navajo Hawai'ian Native Corporation) - New Building | $1,068,411 |
| REIT - 669 Ahua Site Work | $48,722 |
| Salvation Army Kona - Termite Repairs | $44,899 |
| Queen Emma Foundation - New Parking Lot | $46,875 |
| Tesoro Kapolei - Civil Construction for Ultra Low Sulfur Diesel Foundations | $270,350 |
| Coca-Cola USA - Repair Building Columns | $15,476 |
HECO - New Kuahua Substation, Phase 1
![]() |
![]() |
![]() |
||
![]() |
![]() |
![]() |
||
|
A two million dollar project consisting of perimeter dust / security fencing, site clearing and grubbing, demolition, site excavation and backfilling, drilled piers for control house, transformer pads and steel structure footings, sitework for underground electrical ductwork, electrical handholes, and site and structure grounding. Reinforced concrete pier foundations, foundations for CMU property walls and firewalls, control house slab, ramps and walkways, transformer pads and trenches, cable trench, breaker pads, bollards, curbs and gutters.
12” thick CMU property walls with moss rock veneer and 12” thick CMU firewalls, metal embedded plates and anchors, metal entry drive gate, metal trench frames and covers, metal guardrails and bollards, chain link sliding gate and property fencing, landscape and irrigation work, fiberglass reinforced plastic trench grating, bollards painting, site rock fill, vegetation control and asphalt paved driveway.
|
||||
Haig Concrete Parking Structure
![]() |
![]() |
![]() |
||
![]() |
![]() |
![]() |
||
|
This project consisted of a 1,382 s.f. by 1'-2" thick suspended reinforced concrete parking structure and three 20" diameter by 10' thick reinforced concrete slab on grade, reinforced concrete foundations and stair, sitework consisting of foundation excavation and backfilling. Construction featured steep access down to the site, 15 ton Bantam crane assisting in site and concrete work, one sided concrete retaining wall construction with engineered strongback shoring and wall form system, engineered parking deck shoring system, and a combination slick line and boom concrete pumping. |
||||
Advanced Manufacturing Technologies
Navajo Hawaiian Native Corporation New Building
|
|
A million dollar
project, Walker-Moody supplied and built the
Varco-Pruden metal building for
this wood truss manufacturing plant.
Construction included
|
||
![]() |
![]() |
![]() |
|
Tesoro ULSD Civil Installation
|
![]() |
|||
![]() |
|
![]() |
||
![]() |
|
||
|
HECO Substation Sub Base Pearl Harbor |
Haig Concrete Parking Deck |
||
|
|
![]() |
||
|
Tesoro ULSD Civil Installation |
Lyle and John Moody at Hawaiian Electric Job Site |
||